We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.

We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
The project is located in Navoi province, 480 km west of Uzbekistan's capital city, Tashkent. The total installed capacity of the plant is 450 MW, consisting of one block (1 + 1 configuration).
To execute the 450 MW Combined Heat and Power Plant Project, Mitsubishi Hitachi Power System (MHPS) and Mitsubishi Cooperation (MC) formed a consortium, where the power island equipment will be supplied by Mitsubishi Hitachi Power System (MHPS) and Mitsubishi Cooperation (MC) and Çalık Enerji is responsible for the general engineering works, supply of BOP equipment (Water treatment, Waste water treatment, Industrial steam, District heating, Transformers, Switchyard), construction, mechanical and electrical installation works, logistics and BOP commissioning.
Project Title : Navoi-2 Combined Heat and Power Plant Project
Installed Capacity : 473 MW + 100 gcal/h Industrial Steam + 100 gcal/h District Heating
Equipment : Mitsubishi Hitachi Power Systems (MHPS) Gas Turbine (M701F4), + MHPS Steam Turbine + HP & LP HRSG (1+1 Configuration)
Voltage Level : 220 kV
Commencement Date : January 2017
Date of Delivery : January 2020
Employer : Ministry Of Energy Uzbekistan (Uzbekenergo)
Scope : General Engineering Works, BOP Equipment Supply, Construction, Mechanical and Electrical Installation Works