Çalık Enerji
Projects
We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.

We, as Çalık Enerji, are among the leading global energy companies with many successful turn-key contracting projects around the world, since the inception of our company in 1998.
The project is located in Nemengan province, 280 km east of Uzbekistan's capital city, Tashkent. The total installed capacity of the plant is 900 MW which consists of two blocks (2+2 configuration) each with 450 MW installed power.
To execute the 900 MW Combined Cycle Power Plant Project, Mitsubishi Hitachi Power System (MHPS) and Mitsubishi Cooperation (MC) formed a consortium, where the power island equipment will be supplied by Mitsubishi Hitachi Power System (MHPS) and Mitsubishi Cooperation (MC) and Çalık Enerji is responsible for the general engineering works, supply of BOP equipment (Water treatment, Waste water treatment, Water Intake Structure, Transformers, Switchyard), construction, mechanical and electrical installation works, logistics and BOP commissioning.
Project Title : Turakurgan Combined Cycle Power Plant Project
Installed Capacity : 900 MW
Equipment : Mitsubishi Hitachi Power Systems (MHPS) Gas Turbine (M701F4), MHPS Steam Turbine and HP & LP HRSG (2+2 configuration)
Voltage Level : 220 kV
Commencement Date : January 2017
Date of Delivery : April 2020
Employer : Ministry Of Energy, Uzbekistan (Uzbekenergo)
Scope : General Engineering Works, BOP Equipment Supply, Construction, Mechanical and Electrical Installation Works